Refused consent after a disclosure: the 31-day moratorium and court extensions
A firm's nominated officer makes an authorised disclosure to the National Crime Agency, asking for consent to complete a client's property transaction. Within the notice period the NCA tells the nominated officer that consent is refused. The firm receives the notice on 1 December 2026. The firm asks how long it is prevented from completing the prohibited act, and whether the period can be extended if the NCA's investigation is still ongoing.
Which statement correctly describes the position under the Proceeds of Crime Act 2002?
Choose one answer to see the reasoning.
Worked answer
Correct answer B: The moratorium lasts 31 days from notice; a court may extend it 31 days at a time, adding at most 186 days in total.
THE RULE TO REMEMBER
Refusal of consent starts a 31-day moratorium. On a senior officer’s timely application, a court may extend it by up to 31 days at a time, with no more than 186 additional days beyond the initial 31 days: 217 days altogether under these extension powers (POCA ss.335–336A).
Refused consent after a disclosure: the 31-day moratorium and court extensions
Where a nominated officer makes an authorised disclosure, the notice period is seven working days beginning with the first working day after disclosure (POCA section 336(7)). If consent is refused within that period, the initial moratorium is 31 calendar days beginning with the day the nominated officer is given refusal notice (section 336(8)); corresponding provisions for direct disclosures appear in section 335(5)–(6). Under section 336A, a senior officer must apply before the moratorium expires. A court may extend it if the investigation is incomplete, is proceeding diligently and expeditiously, requires further time, and an extension is reasonable. Each extension is limited to 31 days. Section 336A(7) caps the added time at 186 days beyond the initial 31 days, giving 217 days altogether under these extension powers. Expiry removes this consent-based barrier; it does not override another legal restraint.
Why A is wrong: Seven working days is the notice period, not the moratorium period, and the moratorium can be extended.
Why C is wrong: Extensions require a court order on an application by a senior officer, and are capped.
Why D is wrong: Each extension is limited to 31 days and the total extension is limited to 186 days.
Why E is wrong: If consent is refused the firm is not treated as having appropriate consent until the moratorium has expired.
A little more practice done.
Related questions
Buying property you suspect is criminal: the adequate consideration defence in s.329
Does Carys commit an offence under s.329 Proceeds of Crime Act 2002 (acquisition, use and possession)?
Savings built up from tax evasion are criminal property (POCA 2002 s.340)
Which of the following best describes the status of the savings under Part 7 of the Proceeds of Crime Act 2002?
Conducting and settling litigation is not a s.328 POCA arrangement (Bowman v Fels)
Which of the following best describes Mehmet's position under the Proceeds of Crime Act 2002?
A GOOD HABIT, DELIVERED
Tomorrow's question.
In your inbox.
One free question a day, with the answer and reasoning.
No course pitches. Just your daily practice.