Time limit for judicial review of a planning decision (CPR 54.5(5))
On 2 March a local planning authority grants planning permission, under the planning Acts, for a warehouse next to a residential street. A neighbour learns of the decision the same day and wants to challenge it by judicial review on the ground that the authority failed to consider a relevant flood risk report. The neighbour's solicitor and the developer agree in writing that the developer will not take any time point if the claim is filed within three months.
By when must the neighbour file the claim form?
Choose one answer to see the reasoning.
Worked answer
Correct answer C: Not later than six weeks after 2 March, as the grounds first arose then, and that time limit cannot be extended by the parties' agreement.
THE RULE TO REMEMBER
Judicial review of a planning decision by the Secretary of State or a local planning authority must be filed within six weeks of the grounds first arising; JR time limits cannot be extended by agreement.
Time limit for judicial review of a planning decision (CPR 54.5(5))
CPR 54.5(1) sets the general rule that a judicial review claim form must be filed promptly and in any event not later than 3 months after the grounds first arose. But CPR 54.5(4) disapplies that rule in the cases in paragraphs (5) to (7), and CPR 54.5(5) provides that where the application relates to a decision made by the Secretary of State or a local planning authority under the planning Acts, 'the claim form must be filed not later than six weeks after the grounds to make the claim first arose'. CPR 54.5(2) provides that the time limits in the rule 'may not be extended by agreement between the parties'. The grant on 2 March is when the grounds first arose, so the neighbour has six weeks from then, and the parties' agreement has no effect.
Why A is wrong: Planning decisions have a six-week limit, and CPR 54.5(2) prevents the parties extending time by agreement.
Why B is wrong: CPR 54.5(4) and (5) displace the general 3-month rule for decisions of a local planning authority under the planning Acts.
Why D is wrong: Time runs from when the grounds first arose (the grant), not from receipt of reasons, and the parties cannot extend it.
Why E is wrong: The 30-day period is linked to public procurement decisions under CPR 54.5(6), not planning decisions.
A little more practice done.
Related questions
Judicial review time limits: promptly and within three months
Which of the following best describes the time limit for Bilal's claim for judicial review?
Planning enforcement time limit for unauthorised building works in England (TCPA 1990, s.171B)
Which of the following best describes the position on planning enforcement?
Right to a fair hearing before dismissal (Ridge v Baldwin)
Which of the following best describes the board's decision?
A GOOD HABIT, DELIVERED
Tomorrow's question.
In your inbox.
One free question a day, with the answer and reasoning.
No course pitches. Just your daily practice.