Liquidated damages or penalty: the legitimate interest test (Cavendish v Makdessi)

Vantage Software Ltd agreed to install a booking system for Coastal Ferries Ltd by 1 March 2026. Clause 9 provides that if installation is late, Vantage will pay Coastal £50,000 for each day of delay. Both companies took legal advice. Coastal's realistic loss from delay is at most about £2,000 a day, and Coastal has identified no other commercial interest that the clause protects. Installation was completed ten days late, and Coastal claims £500,000 under clause 9.

Which of the following best describes whether clause 9 is enforceable?

Choose one answer to see the reasoning.

  1. Contract · FLK1No. 45

    Damages for negligent misrepresentation and the reverse burden of proof (Misrepresentation Act 1967 s.2(1))

    Which of the following best describes Tom's position if he claims damages under the Misrepresentation Act 1967?

  2. Contract · FLK1No. L047

    Remoteness: losses from special circumstances not communicated (Hadley v Baxendale)

    Which of the following best describes the damages Wren Valley can recover from Swiftline?

  3. Tort · FLK1No. L255

    Pure economic loss caused by a negligent act: power cut damages calculation (Spartan Steel)

    Applying the leading authority on economic loss caused by a negligent act, how much is Forgewell likely to recover from the contractors?