Tomasz Kowalski exchanged contracts to buy a detached house in Exeter for £410,000. The contract incorporates the Standard Conditions of Sale (Fifth Edition, 2018 Revision) without amendment, and no special condition deals with insurance. The seller's buildings insurance is not required by the contract to continue. Tomasz did not arrange his own buildings insurance, intending to do so from completion. A week before completion, a fire caused by a lightning strike seriously damaged the house.

Which of the following best describes Tomasz's position?

Choose one answer to see the reasoning.

  1. Property Practice · FLK2No. L207

    Using the buyer's deposit on the seller's related purchase (SCS 5th ed, condition 2.2.5)

    Which of the following best describes the position under the Standard Conditions of Sale?

  2. Property Practice · FLK2No. 22

    Failure to complete and the notice to complete (SCS 5th ed, condition 6.8)

    Which of the following best describes the effect of the notice to complete?

  3. Property Practice · FLK2No. L209

    Calculating contractual compensation for late completion (SCS 5th ed, condition 7.2)