Ola Bankole sold a house in Northampton to Ben Ashworth for £400,000. The contract incorporates the Standard Conditions of Sale (Fifth Edition, 2018 Revision) and a special condition providing that the contract rate is 8% per annum. Ben paid a deposit of £40,000 on exchange. Completion was delayed and took place 10 days after the contractual completion date. It is agreed that Ben's total period of default was 10 days and that Ola's total period of default (a delay in providing a document she was obliged to supply) was 3 days. Assume a 365-day year.

How much compensation, if any, is payable under condition 7.2, and by whom?

Choose one answer to see the reasoning.

  1. Property Practice · FLK2No. 22

    Failure to complete and the notice to complete (SCS 5th ed, condition 6.8)

    Which of the following best describes the effect of the notice to complete?

  2. Property Practice · FLK2No. L207

    Using the buyer's deposit on the seller's related purchase (SCS 5th ed, condition 2.2.5)

    Which of the following best describes the position under the Standard Conditions of Sale?

  3. Property Practice · FLK2No. L208

    Risk of damage between exchange and completion (SCS 5th ed, condition 5.1.1)

    Which of the following best describes Tomasz's position?