Part payment of a debt (Foakes v Beer)

Gareth, a self-employed joiner, invoiced Ruth £8,000 for fitted wardrobes. The work is not disputed and payment was due on 1 June. Ruth, who could have paid in full, knew that Gareth urgently needed cash to pay his own suppliers. On 1 June she told him: "I will pay you £5,000 if you accept it in full settlement. If you don't, you'll get nothing." Gareth reluctantly signed a note, not executed as a deed, accepting £5,000 "in full and final settlement", and Ruth paid £5,000 by bank transfer that day. Two weeks later Gareth's solicitor wrote demanding the £3,000 balance.

Which of the following best describes whether Gareth can recover the £3,000?

Choose one answer to see the reasoning.

  1. Contract · FLK1No. L029

    Extra pay for performing an existing contractual duty: practical benefit (Williams v Roffey)

    Which of the following best describes whether Kofi can recover the £6,000?

  2. Contract · FLK1No. 45

    Damages for negligent misrepresentation and the reverse burden of proof (Misrepresentation Act 1967 s.2(1))

    Which of the following best describes Tom's position if he claims damages under the Misrepresentation Act 1967?

  3. Contract · FLK1No. 31

    Excluding liability for negligence in a business contract (Unfair Contract Terms Act 1977 s.2)

    Which of the following best describes the effect of clause 9 under the Unfair Contract Terms Act 1977?